Application for Shutdown and Reconnection of Electricity for Maintenance in the UAE
- Temporary Disconnection in Dubai
- Temporary Disconnection in Abu Dhabi
- Temporary Disconnection in Sharjah
- FAQs
Maintenance work in a property may require a temporary electricity disconnection to ensure compliance with safety regulations. In the UAE, residents and businesses can apply for an electricity shutdown and reconnection through the respective government authority. The process is straightforward and can be completed online, although specific requirements and procedures may differ across emirates.
Electricity Shutdown Request for Maintenance in Dubai
In Dubai, electricity disconnection requests for maintenance are managed by the Dubai Electricity and Water Authority (DEWA). The steps to apply, along with the necessary documents, are mentioned below.

Service Steps
The steps to submit an application for temporary disconnection of electricity in Dubai include:
- Log in to the DEWA Smart app or website using a registered account number.
- Download and fill out the ‘Customer Outage Request Form’.
- Upload the form along with other required documents (mentioned below).
- After submitting the application successfully, the customer will receive a reference number.
- The technical team will then review the application.
- Once the review is complete, the customer will be notified via SMS about the application status, whether approved or rejected.
Required Documents
The documents required to submit a temporary disconnection of electricity in Dubai are:
- An undertaking form from the company, stating no changes in the existing load.
- Methodology statement of works.
- Forms of risk assessment.
- Private substation single line diagram.
Electricity Shutdown Request for Maintenance in Abu Dhabi
In Abu Dhabi, applications for electricity shutdown and reconnection are submitted to TAQA Distribution. The service is free of charge and typically takes around 9 working days to process.
Service Steps
The process to apply for the temporary disconnection of electricity in Abu Dhabi includes the following steps:
- Log in to the portal and search ‘Application for Shutdown of Electricity for Maintenance’.
- Duly fill out the form and attach all the required documents (mentioned below).
- Determine the connection type during the field activity. In case of high voltage, conduct an inspection.
- Cross-check all the information and complete the application process.
Documents Required
The following sets of documents are required to submit an application to temporarily shut down the electricity in Abu Dhabi.
- An official letter from the property owner stating the disconnection location and reasons.
- A competency certificate from the Operation & Maintenance Engineer approved by TAQA Distribution.
Electricity Shutdown Request for Maintenance in Sharjah
The Sharjah Electricity, Water and Gas Authority (SEWA) allows individuals and businesses to submit an application for electricity shutdown and restoration through their website. The application takes around 3 working days to complete, and the service fee is AED 600.

Service Steps
Mentioned below are the steps to submit an application for the temporary disconnection of electricity in Sharjah:
- Log in to the SEWA E-service portal or mobile app
- Search ‘Temporary Disconnection’
- Provide all required information and attach the necessary documents
- Review the details and submit the application for processing
Documents Required
The documents required to be submitted with the temporary disconnection application in Sharjah include:
- A request letter from the branch office specifying the need for temporary electricity disconnection.
- Demolition Permit (copy), if the disconnection is required for demolition purposes.
FAQs
Which authority approves electricity shutdown applications?
Electricity shutdown applications are approved by the respective authority in each emirate, such as DEWA in Dubai, TAQA Distribution in Abu Dhabi and SEWA in Sharjah.
Is there a fee for electricity shutdown and restoration requests?
The service is free of cost in Dubai and Abu Dhabi. However, AED 600 is charged for temporary disconnection in Sharjah.
Can an electricity shutdown be scheduled in advance for major maintenance?
Yes, shutdowns can be scheduled ahead of time to align with planned maintenance or construction work.
These are all the ways to submit an application for electricity shutdown and restoration in the UAE. Temporary disconnection allows maintenance work and construction upgrades to be performed safely, whether in residential, commercial or rental properties in the UAE. It is important to plan the shutdown in coordination with the relevant authority for proper scheduling and to prevent hold-ups. Once maintenance is complete, power is reconnected, allowing operations to resume smoothly without delay.