All About How to Apply for Structural Inspection in Dubai
If you’re planning a construction project in Dubai, understanding the process for obtaining structural inspection approval is crucial. Following we will walk you through the steps required to get approval from Dubai Municipality for shoring works, casting concrete slabs and foundations and re-demarcation of buildings. Here’s everything you need to know about applying for a structural inspection in Dubai.
How to Apply for Structural Inspection in Dubai
Follow these steps to get your structural inspection approved by Dubai Municipality:
Step 1: Log in to the Dubai Building Permit System with your credentials.
Step 2: Select ‘structural inspection service’ and upload all necessary documents.
Step 3: You’ll receive a response from the unified inspection committee via Dubai BPS, SMS and email. The reply will indicate if the Dubai Structural Inspection application is accepted with a site inspection date or returned without a visit.
Step 4: Meet the inspection committee at the project site on the specified date.
Step 5: The results will be provided, indicating either partial or full approval, or reasons for rejection. The inspection process typically takes 3 working days.
Documents Required

The key required documents for the Structural Inspection Service include:
- Project’s Consultant Approval Form: Ensure this is completed and submitted as part of your application.
Fees Required
Here is the fee structure to apply for a structural inspection in Dubai.
- Service Fee: Free.
- Site Visit Fees for Re-demarcation or Survey: 100 AED.
- Local Administrative Fees: 5 AED.
- Knowledge and Innovation Fees: 20 AED.
Terms and Conditions to Apply for Structural Inspection in Dubai

Compliance and efficiency are ensured throughout the inspection process.
- Inspections are conducted by a unified committee including members from Dubai Municipality’s Construction Control and Survey Departments.
- Consulting and contracting engineers must attend inspections, except for villa projects and simple additions.
- Once accepted, inspections are scheduled through Dubai BPS. You can obtain the name and contact number of the Dubai Municipality Engineer from the system.
- Survey voucher fees are due with subsequent inspection requests if applicable.
- Mosque projects receive automatic Qibla certificates from the Islamic Affairs & Charitable Activities Department.
- Ensure all building permit requirements are met before applying.
- Partially approved requests may be resubmitted after addressing committee feedback.
- Shoring works inspections cover these stages:
- After excavating the initial 2 metres of natural ground level.
- At anchor levels (if applicable).
- Upon completing the excavation and reaching the foundation level.
- The construction work for FIC must be finished by the contractor and approved during the implementation stage of the structure.
- After confirmation, a task is generated automatically for the Sewerage and Recycled Water Projects Department to link the FIC to the drainage system.
- Approved substation work triggers DEWA HV inspection tasks.
- Consultant Approval Form templates are accessible via Dubai BPS.
- Applications submitted before midnight are scheduled for the following working day if accepted.
- Use Dubai BPS’s message service for inquiries or technical support under relevant categories.
FAQs
Is a structural inspection of steel structures for industrial buildings required?
As per Circular No. 241, structural inspection is not required for steel structures in industrial buildings above ground+1.
At what stage of the project should a structural inspection for a substation be conducted?
Submit your application during the concrete structure implementation phase. The system will automatically include it after checking the approval status. If there is only one substation in your project, it will automatically be linked to all buildings. For multiple substations, ensure you map each one to the respective buildings.
At what stage of the project is it required to apply for a structural inspection application for FIC?
You can apply for structural inspection application for FIC during the concrete structure implementation on the Dubai Municipal website. The system will add it automatically after verifying its approval status. If there is a single FIC in your project, it will be linked to all buildings automatically. For multiple FICs, you need to map each one to the relevant buildings.
How to pay the Dubai Municipality Structural Inspection fee?
You can pay the Dubai Municipality structural inspection fee through the Dubai Municipality App, DubaiNow app, Dubai Smart Government Portal website, or at Al Ansari Exchange branches using cash or a due date cheque.
What are the payment methods to apply for Structural Inspection in Dubai?
Utilise options such as My Wallet, debit credit card, Apple Pay, or Samsung Pay depending on your preference and availability.
By following these steps and ensuring all requirements are met, you can efficiently navigate the process of applying for structural inspection in Dubai. Always refer to the official Dubai Municipality guidelines for more detailed information or specific document requirements.