All About Getting Solar Permits & Connections in Dubai
Solar power has emerged as an eco-friendly source of energy. Driving on the sustainability wave, Dubai continues to encourage the use of solar and other renewable energy sources. However, to ensure safety and compliance with the standards, discerning parties need to obtain solar permits and connections in Dubai. Dubai Electricity and Water Authority (DEWA) provides an easy streamlined process for this service. Let’s walk through the process of getting solar permits and connections in Dubai through the DEWA portal.
Solar Permits and Connections in Dubai
Over the years, the incorporation of solar energy in the UAE can be seen across different sectors. Continuing the tradition, the DEWA Dubai solar panel installation permit allows more people to use this renewable energy source.
With this DEWA service, accredited consultants and contractors can attain solar permits after submitting the required documents. Moreover, the system allows applicants to track progress and interact with DEWA during the process.
Listed below is the process of requesting solar permits and connections in Dubai and all the requirements.
REQUIRED DOCUMENTS

As part of the DEWA solar connection process, applicants need to submit the following documents.
- Affection Plan (required only if the project is located in Dubai’s freezone areas).
- Provide details of the solar module, solar inverter and interface protection unit (If the product is not listed in the DEWA list).
- Design assessment input form in Excel format (.XLSX format only).
- A schedule detailing total connected load, max demand/MDB/SMDB, existing load/KWh meters, proposed solar generation meter, etc. (PDF format only).
- Single-line diagram of the proposed grid-tied solar PV system, including KWh meters, inverters, interface protection system, low voltage distribution system, etc. (PDF format only).
- Site layout showing the location of the proposed solar panels, associated equipment, KWh metering, etc. (PDF format only).
- Production details (KWp and KWh per annum) (PDF format only).
- Installation details for the proposed solar generation meter, PV panels, inverters, MDBs/SMDBs, etc. (PDF format only).
- Wiring layout and sizing of PV system elements (string design, inverters, solar cables, breakers, etc.) (PDF format only).
- Explicit acceptance and agreement to the terms and conditions of the Connection Agreement (PDF format only).
SERVICE STEPS & PROCEDURES
Apply online via the DEWA website. The solar panel approval in Dubai process steps include:
- Stage 1 – Inspection without interconnection
- Stage 2 – Inspection with interconnection
Submission of performance test report for connections above 100KWp.
SERVICE FEES
The service is free of charge.
SERVICE CHANNELS
24/7 through the DEWA website.
SERVICE DELIVERY TIME
- For solar permit -11 working days
- Without Interconnection Inspection – 1 working day from the requested inspection date.
- With Interconnection Inspection – 1 working day from the requested inspection date.
- Invoice issuance: 1 working day.
FAQs
Who Can Submit Getting Solar Permits & Connections Application?
DEWA-enrolled contractors and consultants can apply for this service.
What File Extensions Can I Attach?
The allowed file extensions for this service are PDF and XLSX.
Can I Submit Getting Solar Permits & Connections Manually?
No, the application can only be submitted online.
How can I ensure my solar PV system design meets DEWA’s guidelines?
To ensure your solar PV system design meets DEWA’s guidelines, hire a DEWA-enrolled contractor, submit the required documents online and pass the inspection process.
Are there any incentives or rebates available for solar installations in Dubai?
Yes, the government offers incentives and rebates to help reduce the upfront cost of solar panel installations.
There you have it, the process to obtain solar permits and connections in Dubai. Promoting sustainability, DEWA provides a streamlined process for solar permits. The rising number of DEWA solar-powered homes in Dubai is proof of the authority promoting sustainable energy sources.
Moreover, the many sustainable off-plan projects in Dubai go way beyond ensuring environmental preservation. Browse through these new projects in Dubai to explore a wide list of sustainable off-plan projects.
Stay tuned to dubizzle’s property blog to learn about obtaining real estate permits and more.