All About How to Apply for a Sand Transfer Permit in Dubai
Securing a sand transfer permit is essential for construction projects in Dubai. This permit allows the transfer of sand from one site to another within the emirate, following specific guidelines and conditions. Here’s a step-by-step process of how to apply for a sand transfer permit in Dubai.
Sand Transfer Permit Application Process
Let’s explore these steps to get a sand transport permit in the UAE.
- Step 1: Login: Access the service through the designated online channels. I.e. Dubai Municipality website or application portal.
- Step 2: Application Form: Complete the Dubai sand permit application form in the online system. Upload the necessary documents, pay the required fees and submit your application.
- Step 3: Inspection Appointment: You will receive the site inspection appointment date via email, SMS or through the online system.
- Step 4: Site Inspection: Meet the Dubai Municipality engineer at the project site for inspection.
- Step 5: Permit Issuance: If approved, you will receive the sand transport permit Dubai through the available channels.
Required Documents

For sand transfer from areas under Free Zones authorities and infrastructure projects, the following documents are required for a sand transfer permit in Dubai:
- Affection Plan or Site Plan: This should be for the project from where the sand will be transferred.
- Destination Affection Plan or Site Plan: Required if the applicant chooses the destination instead of the DM engineer.
- Building Permit/Work Order Letter: Applicable for Free Zones Authority projects only or infrastructure projects without a permit.
Sand Permit Fees in Dubai
- Service Fee: AED 200
- Knowledge and Innovation Fees: AED 20
Payment Methods and Options
When applying for a sand transfer permit in Dubai, you have various payment methods and channels to choose from:
Payment Channels
- Smart Applications: Dubai Municipality App and DubaiNow Application
- Online Platforms: Dubai Smart Government Portal
- Al Ansari Exchange: Cash and Postdated Cheque (made payable to Al Ansari Exchange)
Payment Methods
Here’s a breakdown of the various payment methods for your sand transfer permit in Dubai.
- My Wallet: A digital wallet option for secure payments.
- Direct Debit: Automatic debit from your bank account.
- Credit Card: Visa, MasterCard and other major credit cards are accepted.
- Apple Pay: For quick payments using your Apple devices.
- Samsung Pay: Another fast and secure mobile payment method.
By offering multiple convenient payment channels and methods, Dubai Municipality ensures that paying for your sand transfer permit is both flexible and hassle-free.
Service Channels
- Dubai Municipality website – Dubai Building Permits System (Dubai BPS)
- Build in Dubai platform (Build in Dubai)
Terms and Conditions

Here are the essential terms and conditions for obtaining a sand transfer permit. These sand transfer regulations in Dubai help in making the process efficient and compliant with local guidelines.
Application Submission
- Eligibility: The application for Dubai Municipality sand permit must be submitted by the project’s main or secondary contractor registered on the permit.
- Timing: Applications submitted before 12:00 a.m. will be considered and scheduled for the next working day if accepted.
Permit Issuance & Closure
- Issuance: The sand transfer permit is issued for an under-construction site to internal or external destinations specified by Dubai Municipality.
- Closure: After transferring all sand quantities from the project site, the sand transfer permit application must be closed through Dubai BPS within a maximum of 7 working days from the completion of the sand transfer.
NOC Requirement
- Coastal Zone: An NOC for sand excavation within the coastal zone must be obtained through the Public Beaches & Waterways Management Department.
- Certificate Listing: Relevant certificates will automatically appear in the transfer request without needing an attachment.
Destination Specification
- Customer-Determined Destinations: The customer can specify the destination for sand transfer, provided the land belongs to the same project owner or is temporarily used land for the same project.
Resubmission
- Rejected Applications: If the sand transfer permit or Permit Closure Applications are rejected, the contractor must resubmit them after addressing the Municipality’s remarks.
Amendment Requests
- Procedure:
- Login to Dubai BPS and send a general message selecting “Engineering supervision services (Sand Shifting)”.
- Attach supporting documents for the modification request.
- Receive a response (approval/rejection) within 24 hours through the system.
Compliance
- Vehicle Instructions: Sand-transfer vehicles must adhere to the instructions at the destination site.
Inquiries and Support
- Technical Support: For inquiries or technical support, send a general message through the Dubai BPS service, selecting the message category “Engineering supervision services (Sand Shifting)”.
FAQs
What is a sand transfer permit?
A sand transfer permit allows the transfer of sand from one construction site to another within Dubai, following specific guidelines and conditions.
What are the service fees for the sand transfer permit in Dubai?
- Service Fee: AED 200
- Knowledge and Innovation Fees: AED 20
By following these Dubai Municipality guidelines for sand transfer and procedures, obtaining a sand transfer permit in Dubai can be a straightforward process. The process ensures compliance with local regulations and smooth project progress. Moreover, if you are looking for ready-to-move property for sale in Dubai, browse through the listings here.