How to Request a Building Modification Permit in Fujairah
A building modification permit in Fujairah is required whenever changes are made to an existing building, whether architectural, constructional, electromechanical or other structural. This permit ensures that the modifications comply with local regulations and do not affect the safety, structure or approved plans of the property.
A request to modify a building permit in Fujairah must be submitted through licensed consulting offices and is managed by the Engineering and Land Department of Fujairah Municipality. Obtaining this permit keeps your project legal, safe and aligned with municipal standards.
Who Can Apply for a Building Modification Permit in Fujairah
Licensed consulting offices submit requests for modifications to building permits in Fujairah on behalf of property owners, contractors or developers. Modifications may involve:
- Changing the contractor or consultant
- Adding or adjusting structures within or outside plot boundaries
- Demolition or foundation works before modifications
Documents Required for Building Modification Permit in Fujairah

Make sure all documents are prepared and complete to avoid delays:
- Copy of the professional licence
- Existing building permit
- Valid site plan
- Completed modification request form
- Copy of the trade licence for the contractor and consultant
- Approved plans issued by the municipality
- No Objection Certificate (NOC) from Federal Electricity and Water Authority, ETISALAT and Sewage Section (TANQUIA for Fujairah; outside Fujairah: Al Qurayya, Merbh, Gratt, Qidfa, Alhail)
- Supervising letter from the consultant
- Approved plans from the consultant office CD
- Approved elevations from the Survey Section
- Copy of the Emirates ID of the owner, contractor and consultant
- Original signed contract between contractor, owner and certified consultant
- Supervising engineer cards for the consultant and contractor
- List of workers affiliated with the contracting company
- Any additional documents required if changing contractors or consultants, such as:
- Supervision contract copy
- Waiver letters
- Environmental licence for industrial lands
- Certificate of completion of demolition or prior works
- Heavy schedule for commercial or residential buildings
- Adoption fees for external banners if modifications involve signage or external changes
Steps to Request a Building Modification Permit in Fujairah

The application process is mostly digital, but some steps may require visiting the Fujairah Municipality headquarters:
Step 1: Register as a Customer
- Provide a copy of your professional licence, existing building permit and site plan.
- Register via the Fujairah Municipality website, smartFujairah app or at the headquarters.
Step 2: Apply for the Service
- Fill the modification request form and upload all required documents.
- Include contractor and consultant approvals, site plans and NOCs.
Step 3: Submit the Application Online
- Submit the application via the municipality portal, smartFujairah app or in person.
Step 4: Verification of Documents
- Officials check all submitted documents for compliance and completeness.
Step 5: Departmental Approvals
- Land Department – initial approval
- Planning Section – review and approval
- Legal Affairs – if needed for legal cases
- Survey Section – confirm site measurements
Step 6: Enter Permit Data and Pay Fees
- Enter all the details in the building program
- Pay applicable fees online or at the municipality
Step 7: Final Approval and Permit Issuance
- Once all approvals and payments are complete, the modification permit is approved and submitted online.
Why Is a Building Modification Permit Important?
Obtaining a building modification permit ensures that your project:
- Remains compliant with Fujairah Municipality regulations.
- Avoids legal disputes or penalties from unauthorised modifications.
- Confirms that all changes meet safety, structural and architectural standards.
- Keeps coordination smooth between contractors, consultants and regulatory authorities.
- Supports inspections and approvals for utilities and future construction permits.
Without the permit, modifications could face fines, project stoppages or legal action.
FAQs
How can I request a modification to a building permit in Fujairah?
The applications can be submitted via the Fujairah Municipality website or the smartFujairah app, although submission through licensed consultants is mandatory.
Which authority handles building permit changes in Fujairah?
The Engineering and Land Department of Fujairah Municipality handles all approvals and issuance.
What documents are required to modify a building permit in Fujairah?
You must provide approved plans, trade licences, signed contracts, site plans, NOCs and any documents related to contractor or consultant changes.
Requesting a building modification permit in Fujairah is a critical step to ensure that all structural or architectural changes remain legal, safe and compliant. By following the proper steps and submitting complete documentation, you can modify your new project in Fujairah smoothly while avoiding delays or legal issues. Besides, if you are looking for ready-to-move residential properties in Fujairah, check out the listings here.
Stay updated with dubizzle’s property blog for more information on permits, approvals and construction regulations across the UAE.